NEW QUESTION # 26
Which of the following is a DSMD principle?
- A. Build incrementally from Feasibility onwards
- B. Build incrementally in Timeboxes
- C. Build incrementally
- D. Build incrementally from firm foundations
Answer: D
Explanation:
The DSMD (Dynamic Systems Development Method) principle of "Build incrementally from firm foundations" emphasizes the importance of having a solid understanding of the project's foundation before proceeding with incremental development. This principle ensures that each increment is built upon a stable base, which supports the overall project integrity and success.
NEW QUESTION # 27
In a free format Timebox, when should reviews take place?
- A. During the Close.Out phase
- B. Throughout the body of the Timebox.
- C. After the Timebox has been completed
- D. During the Kick-Off phase
Answer: B
Explanation:
In a free format Timebox, reviews should take place: B. Throughout the body of the Timebox3.
NEW QUESTION # 28
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. Share between all of the project roles
- B. Viewed in light of the overriding project goal
- C. The responsibility of the Business Sponsor
- D. Made collaboratively
Answer: B
Explanation:
Principle 1 - Focus on the Business Need suggests that every decision taken during a project should be viewed in light of the overriding project goal. This principle ensures that all decisions align with the main objective of delivering what the business needs, thus maintaining a clear focus on achieving the project's goals.
NEW QUESTION # 29
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. Share between all of the project roles
- B. Made collaboratively
- C. Viewed in light of the overriding project goal
- D. The responsibility of the Business Sponsor
Answer: B
NEW QUESTION # 30
How is Quality ensured during Evolutionary Development?
- A. By continuous verification
- B. By facilitating session to enable a group to work to achieve an agreed goal
- C. By understanding and managing priorities
- D. By managing objectives in a fixed time period
Answer: B
NEW QUESTION # 31
What phase will create Solution increments?
- A. Feasibility
- B. Foundations
- C. Evolutionary Development
- D. Deployment
Answer: C
NEW QUESTION # 32
How should DSDM team measure progress?
- A. Through a project dashboard
- B. Based on what has been delivered at the end of a Timebox.
- C. Through an analysis of the Instrumental Success Factors.
- D. Based on the completion of activities rather than the delivery of products
Answer: B
Explanation:
A DSDM team should measure progress: B. Based on what has been delivered at the end of a Timebox5.
NEW QUESTION # 33
What DSDM product describes how the benefits have actually accrued following a period in live operation?
- A. Project Review Report
- B. Benefits Assessment
- C. Delivery Plan
- D. Prioritized Requirement List
Answer: B
NEW QUESTION # 34
Which plain defined by DSDM, has a planning horizon that includes the end of a project?
- A. High-Level
- B. Detailed
- C. Delivery
- D. Timebox
Answer: C
Explanation:
The Delivery Plan defined by DSDM has a planning horizon that includes the end of the project7. This plan looks towards the future, often months or years ahead, to guide the incremental delivery of the project's outcomes.
NEW QUESTION # 35
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?
- A. Feasibility
- B. Evolutionary Development
- C. Pre-Project
- D. Foundations
Answer: D
Explanation:
The phase in the DSDM process that aims to understand the scope of work and, in broad terms, how it will be carried out, by whom, when, and where is.
NEW QUESTION # 36
When initially creating MoSCoW priorities, what is the primary focus?
- A. Project increment priorities
- B. Iterative Development priorities
- C. Timebox priorities
- D. Project priorities
Answer: D
NEW QUESTION # 37
Which statement about change is correct for DSDM?
- A. Avoid change whenever possible
- B. Change is inevitable and males estimating very difficult
- C. Project operate with a changing world
- D. Change is a symptom of an inability to define requirements properly
Answer: C
NEW QUESTION # 38
In what phase is it first established whether further investigation of the project is justified?
- A. Feasibility
- B. Foundations
- C. Evolutionary Development
- D. Pre-Project
Answer: A
Explanation:
It is during the Feasibility phase that it is first established whether further investigation of the project is justified3. This phase aims to determine if the proposed project is likely to be feasible from both a technical and business perspective.
NEW QUESTION # 39
How does DSDM differ from most other Agile approaches?
- A. It focuses on the entire project lifecycle
- B. It focuses on the collaborative working of teams
- C. It focuses on the development of products
- D. It focuses on the delivery of products
Answer: A
NEW QUESTION # 40
Which competence is NOT required within the Solution Development team?
- A. Business knowledge
- B. Technical expertise
- C. All members to be multi-skilled experts
- D. Willingness to work with other
Answer: C
Explanation:
Within the Solution Development team, it is not required for all members to be multi-skilled experts1. While a diverse set of skills is beneficial, DSDM emphasizes collaboration and the effective use of individual strengths rather than expecting every team member to be an expert in all areas1.
NEW QUESTION # 41
According to the DSDM principle 'Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
- A. Whenever the level of solution quality is known.
- B. During evolutionary development
- C. When the Business Advisor is available
- D. At the start of the project
Answer: D
Explanation:
According to the DSDM principle 'Never Compromise Quality,' the overall level of quality to be delivered within the solution should be agreed at the start of the project5. This principle ensures that quality is not compromised to recover from deviations; instead, the scope of the project will be dynamic6.
NEW QUESTION # 42
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
- A. Foundation Summary
- B. Delivery Plan
- C. Terms of Reference
- D. Management Approach Definition
Answer: D
Explanation:
The DSDM product that reflects the approach to the management of the project as a whole, considering how the project will be organized and planned from a management perspective, is the Management Approach Definition2. This product outlines the overall strategy for managing the project, including aspects such as roles, responsibilities, and processes, ensuring that the project is aligned with its objectives and can be delivered successfully2.
NEW QUESTION # 43
Who is responsible for the application of Principle 8, Demonstrate Control?
- A. Team Leader
- B. Collectively applied by the whole team
- C. Project Manager
- D. The project-level roles
Answer: B
Explanation:
The application of Principle 8, Demonstrate Control, is collectively applied by the whole team4. This principle ensures that there are proper levels of planning, progress measurement, and reporting in place.
NEW QUESTION # 44
What DSDM product is identified as a governance product because if may be used for purposes such as prioritization of a project within a portfolio?
- A. Terms of Reference
- B. Feasibility Assessment
- C. Business Case
- D. Prioritized Requirements List
Answer: A